TOBENE POWER

completed in  2016, this 115MW diesel combined cycle power plant was developed in 2 phases (Phase I  in March 2016 70MW contractual 96MW installed - Phase 2 in December 2016 105MW/115MW installed) developed under a 20-year BOO contract signed with Senelec. The €154m project was completely developed, financed, and realized by Melec PowerGen (25% equity, 75% long term loans, arranged by IFC, with the participation of BOAD, EAIF and FMO). The project was realized by Matelec in partnership with MAN Diesel France who supplied the gensets and contributed to the EPC and O&M. 

The power plant was sold to Azura Power Ltd in September 2019, who entered with MP Energy into a 3-year management contract.